DI-MGMT-81650, DATA ITEM DESCRIPTION: INTEGRATED MASTER SCHEDULE (IMS) (30 MAR 2005) (SUPERSEDES DI-MISC-81183]
DI-MGMT-81650, DATA ITEM DESCRIPTION: INTEGRATED MASTER SCHEDULE (IMS) (30 MAR 2005) (SUPERSEDES DI-MISC-81183]., The Integrated Master Schedule (IMS) is an integrated schedule containing the networked, detailed tasks necessary to ensure
successful program execution. The IMS is vertically traceable to the
Integrated Master Plan (IMP) (if applicable), the Contract Work Breakdown
Structure (CWBS), and the Statement of Work (SOW). The IMS shall be used to
verify attainability of contract objectives, to evaluate progress toward
meeting program objectives, and to integrate the program schedule activities
with all related components. This DID is applicable to development, major
modification, and low rate initial production efforts; it is not typically
applied to full rate production efforts.